PLANNING PROCESS

PLANNING PROCESS

The Comprehensive Plan will be developed over 10 to 12 months. During the Comprehensive Plan process, a master plan for the five focus areas will also be incorporated into the overall Plan. The key tasks for the planning process and schedule are listed below.

Key Tasks & General Schedule

  1. Vision, Goals, and Objectives (July 2023 - October 2023)
    1. Background research and plan review
    2. Demographics, housing, and economic data
    3. Focus area research
  2. Public Engagement - July 2023 - February 2024
    1. Community Survey
    2. Steering Committee Workshops
  3. Land Use and Resiliency - October 2023 - February 2024
    1. Existing land use evaluation
    2. Future land use map
    3. Resiliency element of the Plan update
  4. Plan Development - February - June 2024
    1. Prepare the required elements of the Plan
    2. Prepare plans for the Focus Areas
  5. Implementation Plan - April 2023 - June 2024
    1. Prepare implementation strategies
    2. Prepare revisions to the draft Plan
  6.  Adoption Process - June - August 2024
    1. Planning Commission consideration of the updated Plan
    2. Town Council consideration of adoption